Kakabeka Generating Station

Schedule

DateMilestone
April 2023Start Definition Phase.
December 2023Design Build Contractor hired, Front End Engineering and Design (FEED) starts.
March 2024Complete Value Engineering and select final design.
August 2024Front End Engineering and Design complete.
December 2024Execution Phase approved by OPG.
March 2025Construction starts.
March 2027Construction and Commissioning Complete. Available for service.
Q4 – 2027Project closeout.